The Rough-In Plumbing and Electrical Selections You Must Lock Before Framing
It's natural to want to pick the pretty stuff later, once the walls are up and you can stand in the room. The house doesn't wait for that.
Plumbers and electricians put rough-in parts behind the drywall that depend on exact brands, sizes, heights and power. If you change your mind after inspection, you're not just returning a box. You're cutting open a finished wall.
Here's what I'd lock before framing and rough inspections start.
1. Shower and tub valves. A Kohler thermostatic valve won't take a Delta or Brizo trim kit. The valve goes in the wall early, so you need the brand and setup (rain head, handheld, diverter) up front.
2. Wall-mount faucets and freestanding tub fillers. Both need exact stub-out heights, blocking in the wall and the drain lined up before subfloor or tile backer goes down.
3. Kitchen appliance spec sheets. Your builder needs them for the range, vent hood, built-in fridge, microwave drawer and dishwasher, so they can frame openings, run gas, size circuits and plan makeup air.
4. Vanity sconces, island pendants and bidet outlets. Boxes are cheap to add before drywall and a pain to move after paint. Decide if your mirrors get side sconces or a light bar, how many pendants go over the island, and if you want a GFCI outlet behind the toilet.
5. Exterior doors and windows. They often take 8 to 14 weeks, and framing depends on the rough openings.
If you sort your selections by when they're needed (and not just by what caught your eye at the showroom), the job keeps moving and you don't pay for the same wall twice.